2020 Construction Navigation Page.
January 2020
3rd - Utility trench backfill and some catchup documentation.
3rd - Fire cistern and driveway blast
16th - First upper floor framing, propane tanks, fire cistern.
23rd - More upper floor framing, propane tanks backfilled
30th - Upper Moment frame, Office framing, framers raising a wall
February 2020
19th - Upper Level Framing and Plow Truck.
27th - Roof steel, Garage framing the crane whose outrigger Martin ran into
March 2020
5th - Roof Structure and Slopeable/Skewable Rafter Hangers
12th - Great Room joists, first electrical and Pine Grosbeaks
April 2020
2nd - The parapet walls, incredibly dense clouds and ice crystals!
11th - The La Cantina Doors are on site and the membrane roof
30th - Stair Mockup, pool tile and outside drains
May 2020
12th - Septic field sand base and pool coping
21st - First Lunch at the Views! Under Soffit wood
June 2020
4th - Lower floor ready for concrete and septic system
11th - The last steel beam and the windows arrive!
July 2020
July 23, 2020 - Start of Mechanical
September 2020